Current solicitation results for construction contracts are listed below in contract number order. As a courtesy, they will be posted for 30 days after the award date. For prior solicitation results that are no longer listed on this page, call 410-887-3531.
Contract Number and Title | Contractor and Bid Amount |
---|
15071 SX0 Richlyn Manor Sanitary Sewer Interceptor Rehabilitation, 9950 Richlyn Drive, Perry Hall, Maryland 21128 | - AM-Liner East Inc: $2,486,168
- Insituform Technologies LLC: $1,981,962
- Spiniello Companies: $2,083,300
- Engineer's Estimate: $2,126,050
|
20196 SX0 Glen Echo Interceptor Relief Sewer | No Bidders Yet |
22003 SX0 Bengies Road, Bourque Road and Gladway Road Low Pressure Sewer System—Health Project | - Cossentino Contracting Company Inc: $1,670,700
- General Paving and Contracting Inc: $1,756,001
- Engineer's Estimate: $1,811,050
|
23002 SX0 Long Quarter North Structural Rehabilitation | - AM-Liner East Inc: $25,733,662
- Inliner Solutions LLC: $6,181,082
- Insituform Technologies LLC: $6,960,203
- Spiniello Companies: $6,033,504.20
- Engineer's Estimate: $5,187,400
|
23015 PO0 Western Acceptance Facility Scale House Replacement, 3310 Transway Road, Halethorpe, Maryland 21227 | - North Point Builders of Maryland LLC: $491,100
- Engineer's Estimate: $283,604
|
23111 GX0 Fort Howard Veterans Park Beach Access and Soft Launch, 9115 North Point Road, Fort Howard, Maryland 21052 | - Cianelli Construction Inc: $889,520
- Engineer's Estimate: $767,516
|
23112 GX0 Fleming Park Pier Replacement and Renovations, 641 Main Avenue, Dundalk, Maryland 21222 | - Cianelli Construction Inc: $2,322,500
- Dissen and Juhn LLC: $862,911
- Rehak's Contracting LLC: $1,285,000
- Engineer's Estimate: $1,083,417
|
23195 GX1 GX2 GX3 LED Field Lighting at Banneker Community Center, 5800 through 5895 Old Frederick Road, Catonsville, Maryland 21228, Double Rock Park, 8211 Glen Road, Parkville, Maryland 21234, Middle River Middle School, 800 Middle River Road, Middle River, Maryland 21220 | - Dalton Electric Services Inc.: $1,586,891.94
- Glenelg Construction Inc: $1,319,000
- Lighting Maintenance Inc: $1,494,929.92
- Zerodraft Maryland LLC: $1,211,771
- Engineer's Estimate: $1,662,931
|